Tariff Regulations

Karnataka

The Karnataka Electricity Regulatory Commission has issued the Multi Year Tariff regulations dated 31st May 2006. The primary purpose of these regulations is to determine the tariff in all cases covered under these Regulations.

Karnataka Electricity Grid Code, 2015

Download Principal Document  
Resolution By
KERC
Notification No. and date
M/28/14 Dated 02/02/ 2016
Objectives
1. Defines the relationship between the various Users of the Intra-State transmission system (In-STS), State and Area Load Despatch Centers
2. Facilitation of the optimal operation of the Intra-State grid
3. Facilitation of coordinated and optimal maintenance planning of generation and transmission facilities in the intra-State grid
4. Facilitation of development and planning of economic and reliable intra-State grid in coordination with the National / Regional Grid
5. Facilitation of integration of renewable energy sources by specifying the technical and commercial conditions
[clause 1.2]
Regulations called as
Karnataka Electricity Regulatory Commission (Karnataka Electricity Grid Code) Regulations, 2015
Planning Code for Intra-state Transmission- Introduction
1. The STU shall discharge all functions of planning and coordination relating to intra-State transmission system with CTU, State Governments, Generating Companies, RPC, CEA, licensees and any other person notified by the State Government in this behalf.
2. The STU shall inter-alia provide non-discriminatory open access to its transmission system for use by any licensee or generating company and/or any consumer as and when such open access is provided
3. The STU shall build, maintain and operate an efficient, coordinated and economical intra- State transmission system
[clause 4.1]
Planning Code for Intra-state Transmission- Objective
1. To specify the principles, procedures and criteria which shall be used in the planning and development of the Intra-State Transmission System (In-STS) and the links to Regional Grid
2. To promote co-ordination amongst all Users, STU, CTU, RLDC, CEA in any proposed planning and development of the In-STS
3. To provide methodology and information exchange amongst all Users, STU, SLDC, RLDC, RPC, and CEA for planning and development of the In-STS gird
[clause 4.2]
Planning Code for Intra-state Transmission- Scope
The Planning Criteria applies to STU, all users connected to and/or using and involved in developing the In-STS
[clause 4.3]
Planning Code for Intra-state Transmission- Planning Philosophy
1. STU would formulate perspective plan for intra-State transmission system. These perspective transmission plans would be continuously updated to take care of the revisions in load projections and generation scenarios, considering the seasonal and the time of the day variations.
2.The STU shall carry out planning process from time to time as per the requirement for identification of intra-State transmission system including transmission system associated with Generation Projects, strengthening of intra-State transmission system to absorb / evacuate power from the ISTS.
3. STU shall plan, from time to time, system strengthening schemes need of which may arise to overcome the constraints in power transfer and to improve the overall performance of the grid
4. All Users, CTU, In-SGS and Karnataka Renewable Energy Development Limited (KREDL) and Users shall supply to the STU the desired planning data from time to time to enable them to formulate and finalize its plan
5. Special attention shall be accorded, by STU and Users for adequate compensation for active and reactive power management considering various technological options
6. In case Long Term Access Applications require any strengthening in the intraState transmission system to absorb/evacuate power within the State, the applicant shall coordinate with the STU
7. STU shall have to plan their systems to further evacuate power from ISTS and to optimize the use of the integrated Transmission network
8. the associated intra-State transmission system shall also be discussed and reviewed before implementation during the discussion for finalizing the ISTS proposal
[clause 4.5]
Planning Code for Intra-state Transmission- Criterion
1. The long term applicants seeking transmission service are required to pose their end-to-end requirements well in advance to the STU so as to make-available the requisite transmission capacity
2. The transmission customers are also required to provide a basis for their transmission requirement such as – size and completion schedule of their generation facilityand their commitment to bear transmission service charges
3. Planning of transmission system for evacuation of power from hydro projects shall be done river basin wise
4. In case of highly constrained areas like congested urban / semi-urban area, very difficult terrain etc., the transmission corridor may be planned by taking long term perspective of optimizing the right-of-way and cost.
5. STU shall act as the nodal agency for In-STS planning in coordination with distribution licensees and intra-State generators connected/to be connected in the State grid
6. The various intra-State entities shall be supplied power through the intra-State network only
7. Critical loads such as - railways, metro rail, airports, refineries, underground mines, steel plants, smelter plants, hospitals etc., shall plan their interconnection with the grid, with 100% redundancy and as far as possible from two different sources of supply.
8. Appropriate communication system for the new sub-stations and generating stations may be planned by the STU and implemented by licensees as well as generation developers
[clause 4.6.3]
Planning Code for Intra-state Transmission- Planning Data
Under this Planning Code, the State Generating Companies / IPPs / licensees are to supply data in accordance with the detailed procedures mentioned in the KERC (Terms and conditions for Open Access) Regulations, 2004 as amended from time to time.

[clause 4.7]
Planning Code for Intra-state Transmission- Implementation of Transmission Plan
1.CEA would formulate Perspective Transmission Plan for inter-State transmission system and STU would formulate perspective plan for intra-State transmission system. These perspective transmission plans would be continuously updated to take care of the revisions in load projections and generation scenarios
2.The STU shall carry out planning process from time to time as per the
requirement for identification of intra-State transmission system including transmission system associated with Generation Projects, strengthening of intra-State transmission system to absorb / evacuate power from the ISTS in coordination with CTU to optimize the utilization of the Integrated Transmission network.
3.In addition to the intra-State Transmission system, the STU shall plan, from time to time, system strengthening schemes need of which may arise to overcome the constraints in power transfer and to improve the overall performance of the grid.
4. All Users, CTU, In-SGS and Karnataka Renewable Energy Development Limited(KREDL) and Users shall supply to the STU, the desired planning data from time to time to enable them to formulate and finalize its plan.(Clause 4.7)
Connection Code/ Grid connectivity- Introduction
All Users connected to, or seeking connection to In-STS shall comply with Central Electricity Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007 which specifies the minimum technical and design criteria and Karnataka Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 2004 as amended from time to time.

[clause 5.1]
Connection Code/ Grid connectivity- Objective
1. To ensure the safe operation, integrity and reliability of the grid.
2. To make aware in advance the procedures for connectivity to In-STS and also the standards and condition of the system to be integrated to the grid to any person seeking a new connectivity to the grid.
[clause 5.2]
Connection Code/ Grid connectivity- Scope
The connectivity criteria is applicable to all Users connected to or seeking connection to the InSTS, All such entities shall abide by the CEA (Technical Standards for connectivity to the Grid) Regulations, 2007, in order to ensure that the integrated grid is not adversely affected.

[clause 5.3]
Connection Code/ Grid connectivity- Procedure for connection
1. A User seeking to establish new or modified arrangement of connection to or for use of In-STS, shall submit an application in the standard format (prepared by STU and approved by KERC) to STU /ESCOM.
2. The STU shall process the application for grant of connectivity in accordance with the regulations.

[clause 5.4]
Connection Code/ Grid connectivity- Connection Agreement
Connection agreement includes:
1. The condition requiring both Agencies to comply with the Grid Code.
2. Details of connection technical requirements and commercial arrangements
3. Details of any capital related payments arising from necessary reinforcement or extension of the system, data communication, RTU etc., and demarcation of the same between the concerned parties.
4. A Site Responsibility Schedule.
5. General Philosophy, Guidelines etc on protection and telemetry.

[clause 5.5]
Connection Code/ Grid connectivity- Important technical requirements for connectivity to the grid
1. Reactive Power compensation and/or other facilities shall be provided by Users connected to In-STS to maintain In-STS voltage within the specified range.
2. Reliable and efficient communication systems shall be provided to facilitate necessary information exchange for supervision/control/protection of the grid by the SLDC, under normal and abnormal conditions.
3. Recording instruments such as Data Acquisition System, Disturbance Recorder, Event Logging Facilities, Fault Locator etc., shall be provided and shall always be kept in working condition in the In-STS.
4. A cyber security framework should be inplace as specified in Information Technology Act, 2000 amended from time to time.

[clause 5.9]
Connection Code/ Grid connectivity- Schedule of assets of Regional Grid
STU, other transmission licensees granted licence by the Commission and Generators shall maintain the schedule of their assets and host the same in their respective websites. The same shall be submitted to the Commission as and when called for.
[Clause 5.10]
Corrigendum/ Amendment, if any
No